Mardin Kiziltepe Potable Water Facilities and Transmission Line
- Client : General Directorate of State Hydraulic Works
- Location : Mardin / Turkey
- Scope of Work :
- 34.000,77 m. length Ø1200 mm. diameter and 6.407,93 m lenght Ø1100 mm. diameter GRP pipe transmission lines
- 5 Pump stations
- Chlorination station
- Construction of one 20.000 m³, 2 ea 1.500 m³ and 2 ea 500 m³ water tanks
- Supply and installation of mechanical equipment
- Start Date : 01.01.2006
- Finish Date : 30.12.2010